#Day 1

 

After 2 months we finally got here. At the beginning of the building period we have split up to be as effective as possible. Four of us are staying in Vang and working on the site with the foundations, and the rest of the students are in Begna working with the massivewood boxes and precutting and prefabricating frames. On the site we started the first day with putting up a tent so we have some place to get warm when it gets cold outside. There was still some snow on the site so the rest of the day we mostly shuffled snow. We also decided roughly where the construction is going to be. We got really surprised by the landscape, because the last time we where here there was a lot of snow and everything looked so nice and flat, but when we came here now there were a lot of stones and bushes in the way.